Grid Connection Delays Jeopardize Over €45 Billion in German Investments
A new study reveals that slow grid connection processes in Germany are delaying investments in renewable energy and storage. An estimated €45 billion is at risk of being postponed.

A new study by AFRY, commissioned by the network Beyond Fossil Fuels, indicates that sluggish grid connection procedures are significantly hindering investments in renewable energy and battery storage in Germany. The estimated total value of delayed investments exceeds €45 billion.
The research, which also analyzed eight other European countries, highlights grid connection delays as a widespread issue. Across these nations, renewable energy and battery projects are facing long waits for grid access, effectively blocking approximately €100 billion in potential investments. In Germany alone, an estimated 40,000 projects are caught in this bottleneck.
Key reasons identified for the delays include inefficient regulations for processing connection requests and capacity reservations, lengthy planning and approval procedures, and shortages in supply chains and skilled labor. Deutsche Umwelthilfe has criticized the German government's proposed "grid package," arguing it fails to address the core issue and could further impede investments.
The study suggests implementing measures such as financial incentives for faster grid connection processes and establishing prioritization frameworks for applications, drawing parallels with successful models in countries like the UK and Greece. Germanwatch urges the German government and the Federal Network Agency to hold grid operators accountable through clear directives.